Our production process ensures that work is done in the proper sequence. As our client, you will receive weekly progress pictures so you can watch your project unfold. The job foreman responsible for your home will communicate with you on a regular basis and will always be available for any inquiries you may have during the course of your renovation.

Mobilization and Site Prep
  1. Preconstruction conference: with homeowner, production staff and salesperson to review construction specifications, plans, site conditions and special directions
  2. Homeowner furnishings and personal property packed and moved off site or stored on site
  3. Load up and deliver prep materials, tools and equipment to the site
  4. Cover and protect common areas in condo buildings
  5. Cover and protect home finishes that will not be changed out
  6. Cover and protect house driveway
  7. Identify and prepare area for dumpster, chemical toilet, materials and parking
Demolition
  1. Removal of appliances and other fixtures that are not permanently installed
  2. Removal of plumbing fixtures, light fixtures, bath accessories, door hardware and bathroom glass
  3. Removal of cabinets and countertops
  4. Removal of interior doors and trim
  5. Removal of floor and wall coverings
  6. Removal of drywall
  7. Removal of non-load bearing framing
  8. Removal of exterior siding and roofing
  9. Removal of load bearing structural members
  10. Removal of exterior home features, driveways, landscaping, etc
Concrete & Masonry
  1. Excavation
  2. Soil treatment
  3. Pouring new concrete footings and floors
  4. Building new cement block walls
  5. Pouring new concrete sidewalks and decks
  6. Building stem walls
Rough Carpentry
  1. Frame roofs and exterior walls
  2. Install exterior sheathing
  3. Frame interior walls
  4. Frame ceilings and soffits
  5. Install exterior doors and windows
  6. Install insulation
  7. Install siding and exterior trim
  8. Install fascia and soffit
Rough-in
  1. Run plumbing supply and drain lines
  2. Install shower faucet valves
  3. Install tub and shower drains
  4. Install rubber shower pans
  5. Install electric device boxes
  6. Install recessed light fixture housings
  7. Run electric lines
  8. Run low-voltage lines; telephone, security, television, internet
  9. Run HVAC ductwork
  10. Install HVAC equipment
Drywall & Stucco
  1. Install wall, ceiling and soffit drywall
  2. Install cement board substrate at shower and tub walls
  3. Apply plaster textures to interior concrete ceilings and columns
  4. Apply stucco to exterior surfaces
Cabinets
  1. Install kitchen cabinets
  2. Install bathroom cabinets
  3. Install laundry cabinets
  4. Template countertops
Flooring & Tile
  1. Living area tile, wood, or stone flooring
  2. Shower mud packs, curbs and tile or stone floors
  3. Shower and tub wall tile or stone
  4. Tub decks and aprons
  5. Kitchen backsplashes
  6. Wainscot tile or stone
  7. Template shower enclosures
Finish Carpentry
  1. Install interior doors
  2. Install casing, baseboard, and crown molding
  3. Install specialty trims
  4. Install decorative columns and other architectural features
  5. Install door hardware
  6. Install bathroom accessories
  7. Install appliances
  8. Install Built-ins
  9. Install closets
Countertops
  1. Install kitchen countertops
  2. Install bathroom countertops
  3. Install laundry countertops
  4. Install tile or stone backsplashes at kitchens and bathrooms
  5. Template bathroom mirrors
Trim-out
  1. Install plumbing fixtures and faucets
  2. Install light fixtures and fans
  3. Install electric devices; switches, outlets, dimmers
  4. Install Low-voltage jacks; telephone, television, internet
  5. Install a/c grilles
Painting & finishes
  1. Paint interior walls, ceilings, doors & trim
  2. Paint specialty finishes; faux, venetian plaster
  3. Install wallpaper
Bathroom glass
  1. Shower enclosures
  2. Bathroom mirrors
  3. Medicine cabinets
The final phase of your project is called the walk-thru and punch-out phase. You will meet your project manager at the jobsite and walk through the job to detect any additional work and address any questions you may have regarding the work. Once the punch out list has been completed, your project is 100% complete.